"Aerial view of Fort Jefferson, Florida in 1993" by U.S. National Park Service , public domain
Dry TortugasPreserving Fort Jefferson |
Brochure about Preserving Fort Jefferson at Dry Tortugas National Park (NP) in Florida. Published by the National Park Service (NPS).
featured in
![]() | National Parks Pocket Maps | ![]() |
![]() | Florida Pocket Maps | ![]() |
Dry Tortugas
National Park Service
U.S. Department of the Interior
Dry Tortugas National Park
P.O. Box 6208
Key West, FL 33041
Preserving Fort Jefferson
Preserving Fort Jefferson provides a unique challenge to National Park Service
employees and contractors. The remote marine environment, the logistical
difficulties, and the size of the fort conspire to make restoring the fort seem
daunting. However, highly skilled contractors are now hard at work to insure that
Fort Jefferson will be preserved for future generations.
Protection and
Problems
Fort Jefferson was intended to hold 450
cannons and 1,500 men. The latest technologies
were incorporated into its design to protect the
soldiers here. Specialized iron shutters used to
protect the cannon openings were one of the
many technological advances used here. These
hinged, wrought-iron shutters were placed
between the mortar core of the fort and the
brick façade. A great achievement for their day,
they were first introduced into American forts
in 1857. These shutters were known as “Totten
shutters,” after the coastal fort designer,
General Joseph Totten.
During use, the shutters were unlocked from
the bronze strike plate below. Upon firing the
cannon, gases escaping from the muzzle the
moment before the egress of the shot would
momentarily throw the shutters open. The shutters were carefully balanced so that they would
swing freely and ‘rebound’ into the closed position.
Unfortunately, the very metal that provided
valuable protection to soldiers under fire proved
devastating to the fort itself. In a salt-water
environment, the wraught-iron quickly began to
rust and expand. As the iron rusted, it pushed
the brick apart, causing serious structural damage to Fort Jefferson’s walls. A walk around
the moat shows where large sections of the
fort walls have collapsed into the moat. This is
largely caused by the rusting shutter system.
The founding legislation of Dry Tortugas
National Park mandates the National Park
Service to “protect, stabilize, restore, and
interpret Fort Jefferson, an outstanding
example of nineteenth century masonry
fortification” for future generations. Without
undertaking serious action to stop further
degradation, it became obvious to National
Park Service personnel that the walls of Fort
Jefferson were in serious trouble.
Original Bronze Strike Plate
Preservation Solutions
Dry Tortugas National Park has initiated a multiphased, multi-year preservation project to stabilize Fort Jefferson. The scope of this project is to
carefully remove the existing brick surrounding
the embrasure (cannon) openings on the lower
level in order to gain access to the original iron
elements. When possible,original bricks will be
cleaned and set aside for reuse.
Next, crews will remove all of the rusted iron
elements from the original Totten shutters and
stabilize the exterior walls of Fort Jefferson by
rebuilding the scarp (fort) wall. Concrete made
of local sand and coral - just as used in the
original construction - historic bricks salvaged
during demolition and new replacement bricks
are being used to preserve the historic appearance of the walls. In addition, the parapet and
upper tier embrasure openings will be stabilized
through selective brick replacements and repointing of the mortar joints.
The last step is to restore the Totten shutters “in
kind” per the Secretary of the Interior’s Standards for the Treatment of Historic Properties.
A good example of the “finished product” can
be seen on a walk about halfway around the
moat, where the wall has been restored and the
replica Totten shutters have been installed.
The current phase of the project is concentrated on stabilizing seven embrasures located
on Front 3 and has a target completion date of
July, 2014. In 2013, a contract for this work was
awarded to Stone and Lime Imports, of Brookfield, MA. The demolition and stabilization
work you are witnessing today is being carried
out by skilled masons from Stone and Lime
Imports, Inc.
Pre-Treatment
Working and Living at
Fort Jefferson
Housed within the walls of Fort Jefferson, the
masonry crew of ten to twelve workers per shift
more than doubles the current population of
full-time NPS employee residents. Masons are
on site three weeks and then are off island for a
week. While not on the island, contractors will
most likely return to their families and friends at
home in the Northeast.
Post-Treatment
else the preservationists like to relax when the
day is over by snorkeling, fishing, kayaking,
reading, or even watching TV.
Masons are working full days from early in the
morning until the evening. One added amenity
that Stone and Lime Inc. has budgeted into their
time here is a chef. The chef lives with the crew
members and prepares three meals a day as well
as snacks and refreshments. Additionally, the
chef maintains the quarters in a clean and orderly way, so the masons can focus on their jobs
and not have to spend their down time doing
other work.
As you can imagine, the Dry Tortugas can be a
challenging place to work, so just like everyone
Contact Information
For further information about this project or other
on-going preservation work at Fort Jefferson and
the rest of Dry Tortugas National Park please
contact:
E X P E R I E N C E Y O U R A M E R I C A™
Masonry crew member tooling the joints
Kelly Clark
Exhibits Specialist
Dry Tortugas National Park
Kelly_Clark@nps.gov
01/14